ENHANCING THE CONTRACTUAL PROVISION FOR SUSPENSION OF WORK IN MALAYSIA: A COMPARATIVE ANALYSIS WITH EMPHASIS ON A CASE STUDY OF GOVERNMENT CONTRACT FORM PWD203A

Authors

  • Anisha Shazwani Ahmad Anuar Centre for Building, Construction & Tropical Architecture (BuCTA), Faculty of Built Environment, UNIVERSITI MALAYA
  • Mohd Suhaimi Mohd-Danuri Centre for Building, Construction & Tropical Architecture (BuCTA), Faculty of Built Environment, UNIVERSITI MALAYA
  • Mazura Mahdzir Centre for Building, Construction & Tropical Architecture (BuCTA), Faculty of Built Environment, UNIVERSITI MALAYA
  • Muhammad Hadi Mustafa Centre for Building, Construction & Tropical Architecture (BuCTA), Faculty of Built Environment, UNIVERSITI MALAYA
  • Sharifah Mazlina Syed Khuzzan Kulliyyah of Architecture and Environmental Design, INTERNATIONAL ISLAMIC UNIVERSITY MALAYSIA

DOI:

https://doi.org/10.21837/pm.v22i34.1609

Keywords:

government, contract, suspension, enhancement, provision

Abstract

The government possesses the authority to halt or delay work on-site, either partially or entirely, through the suspension of works as outlined in Clause 50 of the Public Work Department’s PWD203A contract form. However, the global outbreak of the COVID-19 pandemic has revealed the lack of attention towards the proper implementation of work suspension. This study proposes for the improvement of contractual procedures and provisions on the suspension of works of government projects. It addresses the issues pertaining to work suspension in construction projects, examines the existing contract provision in the contract forms, and suggests enhancements of government project contracts. Through a comparative analysis and case study approach focusing on PWD203A, this study identifies the need for establishing clear suspension of work activities, and a fair time restriction mechanism as crucial enhancements to be incorporated into contractual provisions of work suspension. Subsequently, an expert validation process validates the proposed enhancement of the contractual provisions. These findings offer stakeholders valuable insights into practical solutions for more effective management of work suspension of government projects.

Downloads

Download data is not yet available.

References

Augenblick, M., & Rousseau, A. B. (2012). Force majeure in tumultuous times: Impracticability as the new impossibility. The Journal of World Investment Trade, 13(1), 59–75. https://doi.org/10.1163/221190012x621535 DOI: https://doi.org/10.1163/221190012X621535

Cambridge Dictionary. (n.d.). Endemic. In Cambridge dictionary. Retrieved April 8, 2023 from https://dictionary.cambridge.org/dictionary/english/endemic

Che Haron, R., & Arazmi, A. L. (2020). Late Payment Issues of Subcontractors in Malaysian Construction Industry. Planning Malaysia, 18(11), 78-91. https://doi.org/10.21837/pm.v18i11.711 DOI: https://doi.org/10.21837/pm.v18i11.711

Creswell, J. W., & Poth, C. N. (1997). Qualitative inquiry & research design (Fourth Edition): SAGE Publishing.

Chynoweth, P. (2008). Legal research. In A. Knight & L. Ruddock (Eds.), Advanced Research Methods in the Built Environment. Singapore Blackwell Publishing Ltd.

Columbia University Mailman School of Public Health. (2021). Epidemic, endemic, pandemic: What are the differences? https://www.publichealth.columbia.edu/public-health-now/news/epidemic-endemic-pandemic-what-are-differences

Fellows, R., & Liu, A. (2008). Research methods for construction, ( 3rd Ed). Chichester: WileyBlackwell.

Francisco, M. C. (2016). Temporary Suspension of Construction Projects. Proceedings of the Construction Research Congress 2016, 2149-2159. https://doi.org/10.1061/9780784479827.214 DOI: https://doi.org/10.1061/9780784479827.214

Gamil, Y. and Alhagar, A. (2020). The impact of pandemic crisis on the survival of construction industry: a case of covid-19. Mediterranean Journal of Social Sciences, 11(4), 122-128. https://doi.org/10.36941/mjss-2020-0047 DOI: https://doi.org/10.36941/mjss-2020-0047

Hatoum, M., Ali, F., Nassereddine, H., & Sarvari, H. (2021). Analysis of covid-19 concerns raised by the construction workforce and development of mitigation practices. Frontiers in Built Environment, 7, 1-15,https://doi.org/10.3389/fbuil.2021.688495 DOI: https://doi.org/10.3389/fbuil.2021.688495

Lee, A. (2020, April 27). Time and Costs Issues in The Construction Industry Arising from The Movement Control Order. Concentus Law. https://conventuslaw.com/report/malaysia-time-and-costs-issues-in-the-construction/

Maxwell, J. A. (1996). Qualitative Research Design: An Interactive Approach. London, Applied Social Research Methods Series.

Medley GF, Vassall A. When an emerging disease becomes endemic. Science. 2017 Jul 14;357(6347):156-158. doi: 10.1126/science.aam8333. PMID: 28706039. DOI: https://doi.org/10.1126/science.aam8333

Moore, F. (2020, March 26). Will Covid-19 trigger a force majeure clause? Pinsent Masons. https://www.pinsentmasons.com/out-law/guides/covid-19-force-majeure-clause

Mohd-Danuri, M. S., Ishan, Z. M., Mustaffa, N. E., Abd-Karim, S. B., Mohamed, O., & A-Rahmin, R. A. (2015). Dispute Avoidance Procedure: Observing the Influence of Legal Culture towards a Workable Legal System. Pertanika Journal of Social Science and Humanities, 23(2), 509-535.

Muniandy, R. and Mydin, A. (2022). The impact of pandemic covid-19 catastrophes on the survival of construction industry in Penang, Malaysia. International Journal of Academic Research in Business and Social Sciences, 12(1), 243-252. https://doi.org/10.6007/ijarbss/v12-i1/10995 DOI: https://doi.org/10.6007/IJARBSS/v12-i1/10995

Naveen S.K (2020). Is Covid-19 Or the Movement Control Order (“MCO”) A Force Majeure Event In Construction Contract? Thomas Philip.

Ogunnusi, M., Omotayo, T., Hamma-Adama, M., Awuzie, B., & Egbelakin, T. (2021). Lessons learned from the impact of covid-19 on the global construction industry. Journal of Engineering Design and Technology, 20(1), 299-320. https://doi.org/10.1108/jedt-05-2021-0286 DOI: https://doi.org/10.1108/JEDT-05-2021-0286

Porta, M. S. (2014). A Dictionary of epidemiology. Oxford University Press. DOI: https://doi.org/10.1093/acref/9780199976720.001.0001

Robinson, J. (2020, April 2). Pandemics: Definition, Prevention, and Preparation. WebMD. https://www.webmd.com/cold-and-flu/what-are-epidemics-pandemics-outbreaks.

Saeb, A., Mohamed, O., Mohd-Danuri, M. S., & Zakaria, N. (2018). Critical factors for selecting a neutral to support alternative dispute resolution methods in the construction industry. Civil Engineering Journal, 4(1), 11. https://doi.org/10.28991/cej-030965 DOI: https://doi.org/10.28991/cej-030965

Surahyo, A. (2018). Suspension and Termination of Construction in Understanding Construction Contract (pp. 205-214). Springer International Publishing. DOI: https://doi.org/10.1007/978-3-319-66685-3_16

Wittbrodt, B. R. J., & Eaton, L. M. (2009). Project Suspension: What Owners and Contractors Need to Know – Now! Gibbs Gidden. https://www.gibbsgiden.com/wp-content/uploads/2018/07/CMAA-SC-Legislative-Article-Summer-2009-Project-Suspension.pdf

World Health Organization. (2010). Coronavirus disease (COVID-19) pandemic. Retrieved from https://www.who.int/europe/emergencies/situations/covid-19

World Health Organization. (2019). Global action plan on physical activity 2018-2030: more active people for a healthier world. Retrieved from https://www.who.int/publications/i/item/9789241514187.

Yan, S. Z., Mohd-Danuri, M. S., Ismail, N., Mohamed, O., & Ismail, F. (2023). A Qualitative Study on The Doctrine of Privity to Circumvent Its Effect on Subcontractor’s Payment Claim. Planning Malaysia, 21(29). https://doi.org/10.21837/pm.v21i29.1353 DOI: https://doi.org/10.21837/pm.v21i29.1353

Yin, R. K., (1994). Case Study Research Design and Methods: Applied Social Research and Methods Series. (Second ed). Thousand Oaks, CA: Sage Publications Inc.Yin,

Yin, R. K. (2009). Case Study Research: Design and Methods (4th ed.). Thousand Oaks, CA: Sage Publications

Downloads

Published

2024-11-28

How to Cite

Ahmad Anuar, A. S., Mohd-Danuri, M. S., Mahdzir, M., Mustafa, M. H., & Syed Khuzzan, S. M. (2024). ENHANCING THE CONTRACTUAL PROVISION FOR SUSPENSION OF WORK IN MALAYSIA: A COMPARATIVE ANALYSIS WITH EMPHASIS ON A CASE STUDY OF GOVERNMENT CONTRACT FORM PWD203A. PLANNING MALAYSIA, 22(34). https://doi.org/10.21837/pm.v22i34.1609

Most read articles by the same author(s)

1 2 > >>