PROJECT MANAGEMENT CHALLENGES AND CRITICAL SUCCESS FACTORS IN THE REHABILITATION OF ABANDONED HOUSING PROJECTS

Authors

  • Rudy Firdaus Christopher Bernard Sirau SHH Construction Sdn Bhd, PETALING JAYA, SELANGOR
  • Muhamad Zaihafiz Zainal Abidin Centre of Construction and Quantity Surveying, UNIVERSITI TEKNOLOGI MARA, SHAH ALAM
  • Ridzuan Yacob Lebtech Construction Sdn Bhd, SHAH ALAM, SELANGOR
  • Zakwan Ramli Department of Civil Engineering, UNIVERSITI TENAGA NASIONAL (UNITEN)

DOI:

https://doi.org/10.21837/pm.v22i31.1473

Keywords:

Abandoned Housing Project, Project Management, Critical Success factors, White Knights

Abstract

Abandoned housing projects (AHPs) lead to economic losses, social issues, and damage the reputation of responsible authorities. Effective rehabilitation project management is crucial for sustainable urban development. This study explores the challenges and critical success factors (CSFs) throughout the AHP rehabilitation life cycle using qualitative thematic analysis of semi-structured interviews. Identified challenges include communication gaps, inadequate planning and preparedness, deficient risk management, competency issues, documentation problems, and lack of accountability. Key CSFs are effective decision-making, time management, team management, and the role of project managers. The findings provide guidance for policymakers, liquidators, and receivers to improve the implementation of the Housing Development Act for assessing rehabilitation contractors. Addressing these challenges and focusing on the CSFs is essential for successful AHP rehabilitation, mitigating losses, resolving issues, and enhancing the reputation of the authorities.

Downloads

Download data is not yet available.

References

Abdul-Rahman, H., Alashwal, A. M. and Abdullah, A. A. (2016) ‘Abandoned housing projects in Malaysia: Risk management capabilities during rehabilitation’, Archnet-IJAR, 10(2), pp. 153–165. doi: 10.26687/archnet-ijar.v10i2.938. DOI: https://doi.org/10.26687/archnet-ijar.v10i2.938

Abdul-Rahman, H., Wang, C. and Ariffin, N. H. (2015) ‘Identification of Risks Pertaining to Abandoned Housing Projects in Malaysia’, Journal of Construction Engineering, 2015(56), pp. 1–12. doi: 10.1155/2015/524717. DOI: https://doi.org/10.1155/2015/524717

Abdul-Razak, D. (2016) ‘Determinants of Abandoned Housing Projects in Malaysia.’, International Jurnal of Islamic Business Ethics (IJIBE), 1(1), pp. 1-12. DOI: https://doi.org/10.30659/ijibe.1.1.1-12

Abidin, M.Z.Z., & Hassan, F. (2023). Evolution of project management body of knowledge for Malaysian construction industry: A historical mapping. https://doi.org/10.1063/5.0167668 DOI: https://doi.org/10.1063/5.0167668

Akinsiku, O. et al. (2014) ‘Contributions of construction project team to cost overruns: The contractors’ perspective’, Construction Research Congress 2014: Construction in a Global Network - Proceedings of the 2014 Construction Research Congress, pp. 1528–1536. doi: 10.1061/9780784413517.0156. DOI: https://doi.org/10.1061/9780784413517.156

Amoah, A. and Marimon, F. (2021) ‘Project managers as knowledge workers: Competencies for effective project management in developing countries’, Administrative Sciences, 11(4), pp. 1–13. doi: 10.3390/admsci11040131. DOI: https://doi.org/10.3390/admsci11040131

Andersen, B., Samset, K. and Welde, M. (2016) ‘Low estimates – high stakes: underestimation of costs at the front-end of projects’, International Journal of Managing Projects in Business, 9(1), pp. 171–193. doi: 10.1108/IJMPB-01-2015-0008. DOI: https://doi.org/10.1108/IJMPB-01-2015-0008

Ariffin, N. F. et al. (2018) ‘Investigation on factors that contribute to the abandonment of building in construction industry in Malaysia’, E3S Web of Conferences, 34. doi: 10.1051/e3sconf/20183401025. DOI: https://doi.org/10.1051/e3sconf/20183401025

Aziz, E. E. (2015) ‘Project closing: the small process group with big impact’, PMI® Global Congress 2015—EMEA, 2015, pp. 1–7. Available at: https://www.pmi.org/learning/library/importance-of-closing-process-group-9949.

Braun, V., & Clarke, V. (2006) ‘Using Thematic Analysis in Psychology.’, Qualitative Research in Psychology, 3, pp. 77–101. DOI: https://doi.org/10.1191/1478088706qp063oa

Braun, V., Clarke, V., & Terry, G. (2015) ‘Thematic Analysis’, Qualitative Research in Clinical and Health Psychology, pp. 95–113.

Chen, P., Partington, D. and Wang, J. N. (2008) ‘Conceptual determinants of construction project management competence: A Chinese perspective’, International Journal of Project Management, 26(6), pp. 655–664. doi: 10.1016/j.ijproman.2007.09.002. DOI: https://doi.org/10.1016/j.ijproman.2007.09.002

Chin, L. S. and Hamid, A. R. A. (2015) ‘The practice of time management on construction project’, Procedia Engineering, 125, pp. 32–39. doi: 10.1016/j.proeng.2015.11.006. DOI: https://doi.org/10.1016/j.proeng.2015.11.006

Dahlan, N. H. M. (2011) ‘Legal issues in the rehabilitation of abandoned housing projects of the liquidated housing-developer-companies in Peninsular Malaysia’, European Journal of Social Sciences, 23(3), pp. 392–409.

Department, N. H. (2022) List of Abandoned Housing Projects. Available at: https://ehome.kpkt.gov.my/index.php/pages/view/607.

Doraisamy, S. V. and Akasah, Z. A. (2016) ‘A Look into Poor Marketing Strategy on the Issue of Abandoned Housing Projects in Malaysia’, in InCIEC 2015, pp. 243–249. doi: 10.1007/978-981-10-0155-0_23. DOI: https://doi.org/10.1007/978-981-10-0155-0_23

Doraisamy, S. V., Akasah, Z. A. and Khamis, A. (2016) ‘Factors towards the restoration of abandoned residential construction projects in malaysia: A pilot study’, Jurnal Teknologi, 78(5), pp. 71–77. doi: 10.11113/jt.v78.8241. DOI: https://doi.org/10.11113/jt.v78.8241

Ebekozien, A., Abdul-Aziz, A. R. and Jaafar, M. (2022) ‘Low-cost housing demand-supply gap: Government housing planners perspective on possible solutions’, International Journal of Construction Management, 22(9), pp. 1736–1745. doi: 10.1080/15623599.2020.1742627. DOI: https://doi.org/10.1080/15623599.2020.1742627

Osman, M. M., Rabe, N. S., Abdullah, M. F., Rosli, N. F., & Zainudin, F. E. (2017). Housing affordability in the state of Melaka. Planning Malaysia, 15(1), 255–260.

Unit, E. P. (2015). Strategy Paper 6: Providing Adequate and Quality Affordable House. The Economic Planning Unit, Prime Minister’s Department, Malaysia, 1–14. http://rmk11.epu.gov.my/pdf/strategy-paper/Strategy Paper 06.pdf

Eric Morfin (2004) ‘Consistently making strategic project decisions’, Paper presented at PMI Global Congress 2004, 8278. Available at: https://www.pmi.org/learning/library/challenging-issues-making-strategic-project-decisions-8278.

Fox, S. (2001) Effective Communication : Stone Age to e-Comm ., Project Management Institute Annual Seminars & Symposium. Project Management Institute Annual Seminars & Symposium. Nashville, TN: Project Management Institute.

Hilal, N. and Dahlan, M. (2021) ‘Abandoned Housing Projects in Malaysia: A Building Law Perspective’, in 4th International Conference on Research in Social Sciences. Available at: https://www.researchgate.net/publication/335430210.

Hussin, A. A., & Omran, A. (2011) ‘Implication of Non-Completion Projects in Malaysia’, Acta Technica Corviniensis - Bulletin of Engineering, 4(4), pp. 29–38. Available at: http://acta.fih.upt.ro/pdf/2011-4/ACTA-2011-4-03.pdf.

Kaur, S. (2018) ‘Rehabilitating abandoned housing projects’. Available at: https://www.nst.com.my/property/2018/10/418064/rehabilitating-abandoned-housing-projects.

Khattak, M. S. and Mustafa, U. (2019) ‘Management competencies, complexities and performance in engineering infrastructure projects of Pakistan’, Engineering, Construction and Architectural Management, 26(7), pp. 1321–1347. doi: 10.1108/ECAM-05-2017-0079. DOI: https://doi.org/10.1108/ECAM-05-2017-0079

Levin, G. and Rad, P. (2004) Requirements for Effective Project Communications: Differences and Similarities in Virtual and Traditional Project Environments Communication Challenges with Virtual Teams, PMI Global Congress Proceedings- Anaheim, California. PMI® Global Congress. Anaheim, CA: Project Management Institute.

Listokin, D. and Crossney, K. (2006) ‘Best Practices for Effecting the Rehabilitation of Affordable Housing: Technical analyses and case studies’, Vol., 2.

Mohd Fateh, M. A., Arshad, R. A., Ahmad Marzuki, S. M., & Yusof, M. R. (2023). Improvements Of The Communication Between Consultants And Contractors During The Construction Phase In Malaysia. Planning Malaysia, 21(2), 80–103. DOI: https://doi.org/10.21837/pm.v21i26.1261

Nana-Addy, E., Musonda, I. and Okoro, C. (2022) ‘Assessing Causative Characteristics of Abandoned Completed Urban Market Projects in Ghana’, Journal of Construction in Developing Countries, 27(2), pp. 147–161. doi: 10.21315/jcdc-02-21-0028. DOI: https://doi.org/10.21315/jcdc-02-21-0028

National Housing Department. (2022, July 7). Abandoned housing project data as of 7 July 2022 [Data set]. Ministry of Housing and Local Government. https://www.kpkt.gov.my/index.php/pages/view/389

Osman, M. M., Rabe, N. S., Abdullah, M. F., Rosli, N. F., & Zainudin, F. E. (2017). Housing affordability in the state of Melaka. Planning Malaysia, 15(1), 255–260. DOI: https://doi.org/10.21837/pmjournal.v15.i6.241

Project Management Institute (2017) A Guide to the Project Management Book of Knowledge (PMBOK). 6th edn.

Radujković, M. and Sjekavica, M. (2017) Development of a project management performance enhancement model by analysing risks, changes, and limitations, Journal of the Croatian Association of Civil Engineers. and: changes. doi: 10.14256/jce.1866.2016. DOI: https://doi.org/10.14256/JCE.1866.2016

Rahman, H. A. et al. (2013) ‘Abandoned housing projects in Malaysia: Pressing issues during the rehabilitation process’, Archnet-IJAR, 7(1), pp. 65–73.

Rehabimed Method. Traditional Mediterranean Architecture II. Rehabilitation Buildings. (2007).

Seers, K. (2012) ‘Qualitative data analysis’, Evidence-Based Nursing, 15(1), p. 2. doi: 10.1136/ebnurs.2011.100352. DOI: https://doi.org/10.1136/ebnurs.2011.100352

Skumolski, G. J. (2005) Project participant competence. University of Calgary, Alberta, Canada.

Tabish, S. S. and Jha, K. N. (2013) ‘Success traits for a construction project’, Topics in Safety, Risk, Reliability and Quality, 23(10), pp. 147–161. doi: 10.1007/978-94-007-6256-5_6. DOI: https://doi.org/10.1007/978-94-007-6256-5_6

Tripathi, K. and Agrawal, M. (2014) ‘Competency Based Management In Organizational Context : A Literature Review’, Global Journal of Finance and Management., 6(4), pp. 349–356.

Watson, P. (2009) ‘A methodology for attaining and assessing project success for rehabilitation projects’, Journal of Building Appraisal, 4(3), pp. 181–189. doi: 10.1057/jba.2008.36. DOI: https://doi.org/10.1057/jba.2008.36

Yahya, M. A. and Komar, M. Z. H. S. (2016) ‘Factors of Failure for Abandoned Housing Projects’, International Journal of Business and Technopreneurship, 60(3), pp. 393–402.

Downloads

Published

2024-05-31

How to Cite

Bernard Sirau, R. F. C., Zainal Abidin, M. Z., Yacob, R., & Ramli, Z. (2024). PROJECT MANAGEMENT CHALLENGES AND CRITICAL SUCCESS FACTORS IN THE REHABILITATION OF ABANDONED HOUSING PROJECTS. PLANNING MALAYSIA, 22(31). https://doi.org/10.21837/pm.v22i31.1473