ANALYSING CAUSES OF DELAY IN SARAWAK’S CONSTRUCTION INDUSTRY

Authors

  • Chu Sheng Ding 3School of Built Environment, UNIVERSITY OF TECHNOLOGY SARAWAK, MALAYSIA
  • Jiayi Poh 3School of Built Environment, UNIVERSITY OF TECHNOLOGY SARAWAK, MALAYSIA
  • Shi Yee Wong 3School of Built Environment, UNIVERSITY OF TECHNOLOGY SARAWAK, MALAYSIA
  • Saipol Bari Abd Karim Centre for Building, Construction & Tropical (BuCTA) & Faculty of Built Environment, UNIVERSITY OF MALAYA, MALAYSIA

DOI:

https://doi.org/10.21837/pm.v24i44.2287

Keywords:

Delay, Construction Industry, Kruskal-Wallis Test, Sarawak, Malaysia

Abstract

Construction delays are recurring issues in the construction industry. In Malaysia, numerous studies on construction delays have been conducted. However, studies specifically focused on Sarawak, the largest state in Malaysia, remain limited, despite the issue being common in the state. Therefore, the present study aimed to analyse the causes of delay from the perspectives of construction stakeholders in Sarawak. Two objectives were set to achieve the aim: (i) to prioritise the causes of delay and (ii) to examine if there are statistically significant differences in the rankings of causes of delay between clients, consultants, and contractors. A quantitative research method was adopted to collect research data by sending semi-structured questionnaires to the respondents. Eventually, 79 valid responses were collected. The data was analysed using the Descriptive Statistics method for ranking causes of delay and the Kruskal-Wallis test for examining the differences between groups. The results showed that the top three significant causes of delay are labour shortages, increases in material prices, and material shortages. The Kruskal-Wallis test revealed that there is consensus among the construction stakeholders for 65 causes, but differences also exist for 11 causes. The present study provides a comprehensive assessment of 76 causes of delay across different respondent groups. Therefore, the findings could provide valuable insights for the construction stakeholders. Mitigation strategies can be planned before project implementation to reduce the delay issues in Sarawak’s construction industry.

Downloads

Download data is not yet available.

References

Abedin, M. S. Z., Nasir, S. R. M., & Basri, A. (2021). Contractors selection criteria framework for construction project in Klang Valley. Journal of Project Management Practice, 1(1), 22–34. https://doi.org/10.22452/jpmp.vol1no1.2

Adeleke, A. Q., Adeniti, A. W., & Muuka, G. N. (2021). The influence of delay factors on Pahang Malaysian construction industry: A PLS-SEM approach. International Journal of Industrial Management, 11(1), 205–216. https://doi.org/10.15282/ijim.11.1.2021.6120

Aforla, B., Woode, A., & Amoaj, D. K. (2016). Causes of Delay in Highway Construction Projects in Ghana. Civil and Environmental Research, 8(11), 69–76.

Ahmed, S. K. (2024). How to choose a sampling technique and determine sample size for research: A simplified guide for researchers. Oral Oncology Reports, 12, 100662. https://doi.org/10.1016/j.oor.2024.100662

Albtoosh, H. A. M., & Alkhamis, T. M. (2021). Administrative policies to reduce the negative impact of variation orders on Jordanian construction projects. American Journal of Industrial and Business Management, 11, 329–340. https://doi.org/10.4236/ajibm.2021.114021

Aldammark, M. M., Hamzah, N., & Khoiry, M. A. (2025). Delay in construction offices building: A systematic review. Jurnal Kejuruteraan, 37(5), 2453–2467. https://doi.org/10.17576/jkukm-2025-37(5)-33

Alshihri, S., Al-Gahtani, K., & Almohsen, A. (2022). Risk Factors That Lead to Time and Cost Overruns of Building Project in Saudi Arabia. Buildings, 12(7), 902. https://doi.org/10.3390/buildings12070902

Aminorlah, A. I., Rahim, N. A., Mohamed, Z., & Mazlan, A. N. (2023). Critical delay factors in typical physical projects: The case of the Ministry of Home Affairs in Malaysia. Journal of Construction in Developing Countries, 28(2), 57–59. https://doi.org/10.21315/jcdc-01-22-0014

Amoah, K. B. O., Okere, G., & Deshpande, A. (2024). Construction delay analysis: Causes, impacts, and mitigation strategies. Journal of Civil Engineering Research, 14(1), 1–9. https://doi.org/10.5923/j.jce.20241401.01

Amzafi, N. H., Ishak, S. A., Rahim, M. A., Amlus, M. H., Rani, H. A., Syammaun, T., Mokhtar, H., & Ayob, A. (2024). A systematic review of the causes and effects of variation orders in sustainable construction in developing countries. International Journal of Integrated Engineering, 16(4), 188–203. https://doi.org/10.30880/ijie.2024.16.04.023

Arantes, A., & Ferreira, L. M. D. F. (2020). Underlying causes and mitigation measures of delays in construction projects: An empirical study. Journal of Financial Management of Property and Construction, 25(2), 165–181. http://dx.doi.org/10.1108/JFMPC-03-2019-0029

Assaf, S., Hassanain, M. A., & Abdallah, A. (2018). Review and assessment of the causes of deficiencies in design documents for large construction projects. International Journal of Building Pathology and Adaptation, 36(3), 300–317. https://doi.org/10.1108/IJBPA-10-2017-0050

Aziz, M. K. A., & Prasetijo, J. (2022). The cause and effect of delay in LRT3 depot construction project. Progress in Engineering Application and Technology, 3(2), 783–789.

Azlan, H. Z., Khaderi, S. S., & Bakri, A. S. (2024). Critical factors influencing bid mark-up decision in public street project – A review. Built Environment Journal, 21(1), 30–44. https://doi.org/10.24191/bej.v21i1.480

Bano, B., Shakimon, M. N., & Roslan, S. N. A. (2023). Investigation of the factors influencing the construction delays in Klang Valley Malaysia. International Journal of Infrastructure Research and Management, 11(2), 108–116.

Bariono, N. S. E., & Kamaruding, M. (2025). Initiatives to overcome the issues and negative impacts on the involvement of foreign laborers in the Malaysian construction industry. Jurnal Kejuruteraan, 37(2), 855–867. https://doi.org/10.17576/jkukm-2025-37(2)-24

Bohari, A. A. M., Ikau, R. A., Budin, H., Hadi, N. A., & Chan, V. S. L. (2021). The key criteria in deciding to tender for construction projects. International Journal of Integrated Engineering, 13(3), 229–235. https://doi.org/10.30880/ijie.2021.13.03.028

Borneo Post Online. (2025a). RM5.68 mln S’wak Infra hall project faces delay, ministry steps up monitoring. Borneo Post Online. https://www.theborneopost.com/2025/06/06/rm5-68-mln-swak-infra-hall-project-faces-delay-ministry-steps-up-monitoring/

Borneo Post Online. (2025b). RM74 mln Dalat road project faces delay, meeting set for April 30. Borneo Post Online. https://www.theborneopost.com/2025/04/23/rm74-mln-dalat-road-project-faces-delay-meeting-set-for-april-30/

Borneo Post Online. (2025c). DCCI: Labour shortage in Sarawak linked to local labour gap, ageing population. Borneo Post Online. https://www.theborneopost.com/2025/01/09/dcci-labour-shortage-in-sarawak-linked-to-local-labour-gap-ageing-population/

Borneo Post Online. (2025d). Sheda advisor: Developers brace for higher costs as SST expansion hits Sarawak’s construction sector. Borneo Post Online. https://www.theborneopost.com/2025/07/03/sheda-advisor-developers-brace-for-higher-costs-as-sst-expansion-hits-sarawaks-construction-sector/

Borneo Post Online. (2026). Shortage of construction materials in Sabah, Sarawak needs private sector support, says Ahmad Maslan. Borneo Post Online. https://www.theborneopost.com/2026/04/09/shortage-of-construction-materials-in-sabah-sarawak-needs-private-sector-support-says-ahmad-maslan/

Chen, Z., Hammad, A. W. A., & Alyami, M. (2024). Building construction supply chain resilience under supply and demand uncertainties. Automation in Construction, 158, 105190. https://doi.org/10.1016/j.autcon.2023.105190

DayakDaily. (2025a). Three ‘sick’ housing projects in Kuching finally completed after years of delay. DayakDaily. https://dayakdaily.com/three-sick-housing-projects-in-kuching-finally-completed-after-years-of-delay/

DayakDaily. (2025b). All delayed, ‘sick’ Rural and Regional Dev’t projects in Sarawak must be implemented under 13MP – DPM Zahid. DayakDaily. https://dayakdaily.com/all-delayed-sick-rural-and-regional-devt-projects-in-sarawak-must-be-implemented-under-13mp-dpm-zahid/

DayakDaily. (2025c). Cabinet paper to tailor Sarawak projects to State-specific needs, says DPM Fadillah. DayakDaily. https://dayakdaily.com/cabinet-paper-to-tailor-sarawak-projects-to-state-specific-needs-says-dpm-fadillah/

Department of Statistics Malaysia. (2025). Special release for building and structural works. Department of Statistics Malaysia. http://www.statistics.gov.my/uploads/release-content/file_20251209155001.pdf

Department of the Premier of Sarawak. (2025a). Sarawak faces shortage of skilled workers. Department of the Premier of Sarawak. https://premierdept.sarawak.gov.my/web/subpage/news_view/15258/UKAS

Department of the Premier of Sarawak. (2025b). Federal government discusses solutions to delayed projects in Sarawak. Department of the Premier of Sarawak. https://premierdept.sarawak.gov.my/web/subpage/news_view/15205/UKAS

Dunn, O. J. (1964). Multiple comparisons using rank sums. Technometrics, 6(3), 241–252. https://doi.org/10.1080/00401706.1964.10490181

Faizal, N. F., Kasim, N., Ang, P. S. E., Ismail, Z., & Namara, I. (2025). Decision support system of project delay for improving project performance in construction project. Journal of Technology Management and Business, 12(1), 137–155.

Free Malaysia Today. (2025a). Education ministry tops list of critically delayed projects under 12MP, says A-G report. Free Malaysia Today. https://www.freemalaysiatoday.com/category/nation/2025/10/06/education-ministry-tops-list-of-critically-delayed-projects-under-12mp-says-a-g-report

Free Malaysia Today. (2025b). Sarawak needs more skilled workers, says Deputy Premier. Free Malaysia Today. https://www.freemalaysiatoday.com/category/nation/2025/03/25/sarawak-needs-more-skilled-workers-says-deputy-premier

Gashahun, A. D. (2020). Causes and effects of delay on African construction projects: A State of the Art Review. Civil and Environmental Research, 12(5), 41–53.

Goh, K. Z. H., Wong, S. Y., & Low, W. W. (2023). Factors causing dispute in construction industry: Contractor’s perspectives. Journal of Surveying, Construction and Property, 14(1), 14–26. https://doi.org/10.22452/jscp.vol14no1.2

Golzar, J., Noor, S., & Tajik, O. (2022). Convenience sampling. International Journal of Education and Language Studies, 1(2), 72–77. https://doi.org/10.22034/ijels.2022.162981

Hailu, A. Y., Mohammed, I., Alemu, D., & Gesese, A. (2023). Construction project delay factors of public universities in Ethiopia: A structural equation modeling approach. Journal of Economics, Management and Trade, 29(3), 16–34.

Hair, J. F., Black, W. C., Babin, B. J., & Anderson, R. E. (2010). Multivariate data analysis (7th ed.). Pearson.

Hasib, S. S. B., & Al-Kilidar, H. (2021). Identifying project delay factors in the Australian construction industry. World Academy of Science, Engineering and Technology International Journal of Structural and Construction Engineering, 15(3), 135–141.

Hisham, S. N. A., & Yahya, K. (2016). Causes and effects of delays in construction industry. Construction Management, Geotechnics and Transportation, 2, 78–89.

Hoo, B. X., Khalid, Z., Saarani, P. S. N., Sarpin, N., & Omar, R. (2024). Study on the factors to improve productivity and efficiency of construction workers in Klang Valley. Research in Management of Technology and Business, 5(1), 1534–1551. https://doi.org/10.30880/rmtb.2024.05.01.101

Hoque, I., Safayet, A., Rana, J., Bhuiyan, A. Y., & Quraishy, G. S. (2021). Analysis of construction delay for delivering quality project in Bangladesh. International Journal of Building Pathology and Adaptation, 41(2), 401–421. https://doi.org/10.1108/IJBPA-03-2021-0032

Ismaeil, E. M. H., & Sobaih, A. E. E. (2024). A proposed model for variation order management in construction projects. Buildings, 14, 726. https://doi.org/10.3390/buildings14030726

Joharudin, N. F. M., Makmor, M., Zulkifly, U. K. Z., Ahamad, A. H., & Nasir, M. F. M. (2026). Managing supply chain disruptions in private construction projects: Insights from Malaysian contractors. Built Environment Journal, 23(2), 608–621. https://doi.org/10.24191/bej.v23i2.11338

Kouvelis, P., Chen, X., & Xia, Y. (2023). Managing material shortages in project supply chains: Inventories, time buffers, and supplier flexibility. Production and Operations Management, 32, 3717–3735. https://doi.org/10.1111/poms.14059

Lim, Z. Q., Mohd-Rahim, F. A., Mahdzir, M., Mustafa, M. H., & Alashwal, A. (2025). Design errors’ impact on construction project costs. Journal of Construction in Developing Countries, 30(2), 25–47. https://doi.org/10.21315/jcdc.2025.30.2.2

MalayMail. (2023). Health clinic construction delayed in Sarawak due to raw material shortage, says deputy health minister. MalayMail. https://www.malaymail.com/news/malaysia/2023/11/20/health-clinic-construction-delayed-in-sarawak-due-to-raw-material-shortage-says-deputy-health-minister/103138

Masrom, M. A. N., Chong, B. Y., Mohamed, S., Yassin, A. M., Seow, T. W., Haron, R. C., & Chan, M. (2021). Determining critical contributory factors of payment default in residential construction projects. International Journal of Integrated Engineering, 13(5), 200–210. https://doi.org/10.30880/ijie.2021.13.05.021

Memon, A. H., Rahman, I. A., Akram, M., & Ali, N. M. (2014). Significant factors causing time overrun in construction projects of Peninsular Malaysia. Modern Applied Science, 8(4), 16–28. https://doi.org/10.5539/mas.v8n4p16

Memon, M. A., Thurasamy, R., Ting, H., & Cheah, J. H. (2025). Convenience sampling: A review and guidelines for quantitative research. Journal of Applied Structural Equation Modeling, 9(2), 1–15. https://doi.org/10.47263/JASEM.9(2)01

Mohammad, N., Hamzah, Z., & Mokhtar, N. A. (2022). Control of variation orders in the construction of residential projects in Malaysia. Planning Malaysia: Journal of the Malaysian Institute of Planners, 20(2), 14–21.

Mydin, M. A. O., Sani, N. M., Salim, N. A. A., & Alias, N. M. (2014). Assessment of influential causes of construction project delay in Malaysian private housing from developer’s viewpoint. Emerging Technology for Sustainable Development Congress (ETSDC 2014), 3. https://doi.org/10.1051/e3sconf/20140301027

Office of the Premier of Sarawak. (2023). Premier: No cement shortage in S’wak, just rapid infrastructure dev. Office of the Premier of Sarawak. https://premier.sarawak.gov.my/web/subpage/news_view/5528#:~:text=Source%20of%20News:%20The%20Borneo,cement%20supply%20chain%20in%20Sarawak.

Opeyemi, B. A., Sunday, I. K., Abdullahi, I., Abiodun, S. M., & Agada, D. I. (2022). An assessment of the factors influencing time performance of educational building projects in Ondo State, Nigeria. In Proceedings of the 5th International African Conference on Current Studies (pp. 167–178). Cairo, Egypt.

Othman, A., & Ismail, S. (2014). Delay in government project delivery in Kedah, Malaysia. Recent Advances in Civil Engineering and Mechanics, 248–254.

Rahim, F. A. M., Ling, K. G., Zainon, B., & Yusof, N. S. M. (2025). Minimizing the risk of cost overrun in building construction project during pre-contract stage. Planning Malaysia: Journal of the Malaysian Institute of Planners, 23(6), 105–118. https://doi.org/10.21837/pm.v23i39.1899

Razali, N. K., Yong, N. H., Yong, N. F., & Hasim, N. (2025). Government initiatives to promote BIM adoption in Sarawak: A systematic literature review. Journal of Advanced Research in Social and Behavioural Sciences, 41(1), 124–141. https://doi.org/10.37934/arsbs.41.1.124141

Romzi, N. A., & Doh, S. I. (2022). Underlying causes of construction project delay: A review. Construction, 2(2), 7–11. https://doi.org/10.15282/construction.v2i2.7775

Rubin, U., Sarpin, N., Shafii, H., Masrom, M. A. N., & Ismayatim, N. (2024). The issue of labor shortage affecting the delay in the Sarawak Pan Borneo Highway construction project. Research in Management of Technology and Business, 5(1), 1415–1427. https://doi.org/10.30880/rmtb.2024.05.01.093

Sa’ad, M. H. B. M., Herman, S. S. B., & Azlan, A. B. (2022). The delay issues in the Malaysian construction industry and benefits of industrial revolution 4.0 (I.R 4.0) to mitigate issues for project managers. In Proceedings of the 9th International Conference on Management and Muamalah 2022 (pp. 416–424).

Sarawak Tribune. (2025a). Delayed Sejingkat Bridge targeted for completion by June 2026. Sarawak Tribune. https://www.sarawaktribune.com/delayed-sejingkat-bridge-targeted-for-completion-by-june-2026/

Sarawak Tribune. (2025b). Ministry resolves seven-year delay in sick housing project. Sarawak Tribune. https://www.sarawaktribune.com/delayed-bintulu-housing-project-back-on-track-after-ministrys-intervention/

Sarpin, N., & Ramesh, S. (2024). The contribution of subcontractor’s performance towards project success: Main-contractor perspective. Journal of International Business, Economics and Entrepreneurship, 9(1), 12–23. https://doi.org/10.24191/jibe.v9i1.893

Shahron, S. A., Basher, M. A., Musa, S., & Mohamed, O. (2023). Financial issues and impacts on construction industry in Kedah and Perlis. PaperASIA, 39(6b), 58–62. https://doi.org/10.59953/paperasia.v39i6(b).34

Sharuddin, N. M., Azman, M. A., Samad, Z. A., & Rodzi, R. M. (2024). Relationship between schedule delay factors and project performance in civil engineering works. Built Environment Journal, 21(Special Issue), 23–26. https://doi.org/10.24191/bej.v21iSpecialIssue.2424

Shehu, Z., Endut, R., & Akintoye, A. (2014). Factors contributing to project time and hence cost overrun in the Malaysian construction industry. Journal of Financial Management of Property and Construction, 19(1), 55–75. http://dx.doi.org/10.1108/JFMPC-04-2013-0009

Taber, K. S. (2018). The use of Cronbach’s alpha when developing and reporting research instruments in science education. Research in Science Education, 48, 1273–1296. https://doi.org/10.1007/s11165-016-9602-2

Tahmasebinia, F., & Song, V. (2022). Significant factors causing delay in the Cambodian construction industry. Sustainability, 14, 3521. https://doi.org/10.3390/su14063521

Tariq, J., & Gardezi, S. S. S. (2023). Study the delays and conflicts for construction projects and their mutual relationship: A review. Ain Shams Engineering Journal, 14(1), 101815. https://doi.org/10.1016/j.asej.2022.101815

Theng, S., & Techapeeraparnich, W. (2020). Ranking of Risk Factors Causing Delays on Building Construction Project in Cambodia. In Proceedings of RSU International Research Conference (pp. 919–928). Rangsit University, Thailand.

Thorat, S., Khandere, M. A., & Kanase, A. K. (2017). Exploratory study of causes and effects of delay in Indian residential projects. International Research Journal of Engineering and Technology, 4(6), 2302–2311.

Ting, H., Memon, M. A., Thurasamy, R., & Cheah, H. W. (2025). Snowball sampling: A review and guidelines for survey research. Asian Journal of Business Research, 15(1), 1–15. https://doi.org/10.14707/ajbr.250186

Tomczak, M., & Tomczak, E. (2014). The need to report effect size estimates revisited. An overview of some recommended measures of effect size. Trends in Sports Sciences, 1(21), 19–25.

Ullah, K., Khan, M. S., Lakhiar, M. T., Vighio, A. A., & Sohu, S. (2018). Ranking of effects of construction delay: Evidence from Malaysian building projects. Journal of Applied Engineering Sciences, 8(21), 79–84. https://doi.org/10.2478/jaes-2018-0011

Yap, J. B. H., Goay, P. L., Woon, Y. B., & Skitmore, M. (2021). Revisiting critical delay factors for construction: Analysing project in Malaysia. Alexandria Engineering Journal, 60(1), 1717–1729.

Zagia, F., Kajewski, S., Omrani, S., & Motamedisedeh, O. (2025). Prioritizing the key causes of construction project delay in different countries: A cross-sectional analysis of different project types. International Journal of Construction Management, 1–26. https://doi.org/10.1080/15623599.2025.2568103

Zhang, S., Sunindijo, R. Y., Wang, J., Su, Z., Ke, Y., & Liu, X. (2025). The causation of design error in the construction industry: A multistakeholder perspective. Journal of Performance of Constructed Facilities, 39(1), 04024055. https://doi.org/10.1061/JPCFEV.CFENG-4862